Security and privacy restored at Shugsep Nunnery

Since late 2019, the Tibetan Buddhist nuns at Shugsep Nunnery and Institute wanted to proceed with two big repair projects, but both had to be put on hold because of the pandemic.

In February 2021, as the number of coronavirus cases in the area dropped, the nuns were finally able to undertake two projects with a significant impact on their daily lives. The nuns are so grateful to the donors that made this work possible.

What a Relief! New Security Wall for the Nunnery

The nuns are finally safe from prying eyes and dangerous intruders.

When Shugsep Nunnery was first built, it was in a small village at the end of a tiny road. However, over time, several new buildings have come up around the nunnery including a large private school with its entrance immediately behind the nunnery grounds.

Fortunately, in designing the nunnery, the plans left a 20-metre distance between the upper housing wing and the back boundary wall. This area is mostly covered in old mango trees. The trees form a buffer between the nuns’ living quarters and the activity of the nearby private school.

new wall behind Shugsep Nunnery

Privacy and security have been restored at Shugsep Nunnery and Institute thanks to this new wall funded by Tibetan Nuns Project supporters. The nuns are extremely grateful.

However, because the level of the road behind the nunnery grounds was raised by the school, the perimeter wall which was once an 8-foot-high wall and topped with barbed wire was reduced to just 4 feet above road level. This meant that the nuns lost their privacy and schoolchildren, bus drivers, and passers-by could clearly see over the wall into the nunnery.

Although the nuns tried to be tolerant of being stared at, they were reluctant to sit on their verandas to study and they felt inhibited about using the bathrooms at the end of the building. The situation also became dangerous. There were some frightening intrusions into the nunnery by youths who broke down the barbed wire and climbed over the wall. It was clear that the wall had to be improved as soon as possible.

However, because of the COVID-19 pandemic, the nuns could not raise the height of the wall in 2020. Fortunately, the adjacent private school was closed for the whole year.

The nuns were able to start the work in February 2021, adding another 4 feet in height along the length of the wall in front of the school. Now that the neighboring school has reopened, the view into the nunnery is blocked and the nuns feel very relieved.

Shugsep Nunnery and Institute

The nuns have tidied the area behind the newly repaired wall. They can now use this secluded, shady area under the mango trees as a place to practice Tibetan Buddhist debate.

It is gratifying to see how the nuns’ relief has translated into their efforts to make the area pleasant. The nuns have worked hard clearing and levelling the area under the trees so they will be able to use it as a shady debate yard.

The nuns are extremely grateful to have their security and privacy restored.

Project approved to start: 10/12/19. Start delayed due to the pandemic.
Project started: 15th January 2021
Project completed: 22nd February 2021
Total cost: Rs. 1,17,715  which is roughly US $1,620
Scope of work:
A.  Raised wall height with dressed stone, sand, bajari, and cement. Rs. 1,01,715 ($1,400)
B.  Provided and fixed poles Rs. 11,000 ($151)
C.  Removed old fence wire and re-fixed wire  Rs. 5,000. ($69)

No More Leaks: Water Tank Repair

Shugsep Nunnery depends on the large double-story concrete water tank on the slope behind the nuns’ housing wing. The municipal water lines do not provide enough water to cover the needs of the nunnery and the tank is fitted so that it can be supplied by pumping from the bore well. After 12 years, the tank itself was in a very dilapidated condition and was seriously leaking.

After researching the best way to repair the tank, the nuns hired a local contractor to re-seal the inside of the tank with marble chips and to re-plaster and paint the outside. They also needed to repair and replace the  plumbing lines.

The nuns had to purchase the marble chip material as a truckload from Rajasthan. The plan was to use the same material to seal the Dolma Ling Nunnery and Institute water catchment. The order for both nunneries was placed in October 2019 and, when the materials arrived, they were stored at Dolma Ling because their water project repairs had to be done first. The Dolma Ling work was completed in December 2019.

repair projects, painted water tanks at Shugsep Nunnery and Institute.

The newly repaired and painted water tanks at Shugsep Nunnery and Institute. The work was delayed for a year due to the pandemic and the nuns are very grateful that the work was able to be completed.

Due to the COVID-19 pandemic, the work of repairing the Shugsep water tank was put off until the end of 2020 when, with the reduced virus caseload, the nuns felt secure enough to agree to allow workmen into the back of the nunnery compound. The work was done in stages, fixing one tank and then the other so that the nuns always had some water supply.

The new water tanks look very clean and professionally repaired. The nuns are very happy that the water tanks are working well and no longer leak. The nuns are very grateful to the Tibetan Nuns Project donors for making this improvement to their facilities possible.

Project approved to start 10/10/19. Start delayed due to pandemic.
Project started: 15th December 2020
Completed: 1st February 2021
Cost of contract:  Rs.169,720 (approximately $2,335)
Scope of work:
A. Provided and laid marble chips including chipping off and cleaning the old plaster and flooring. Rs. 1,36,720 ($1,881)
B. Removed and replaced water lines and fittings, gate valves unions, etc. Rs. 19,000 ($261)
C. Painted external areas of tanks, pillars etc. using waterproof paint: Rs. 14,000 ($193)